Both give a safety stock figure; pick the one that matches how you plan.
Chance of not stocking out during a lead time, under a normal-demand assumption.
Historical day-to-day spread; 0 = perfectly steady demand.
Reorder point
949 units
Safety stock
109 units
Lead-time demand
840 units
Days of cover at reorder
7.9 days
Rounding: figures are shown rounded to whole units; the underlying math keeps decimals.
Formula: reorder point = (average daily demand × lead time in days) + safety stock. Safety stock is either z × standard deviation × √lead time (service-level method, which assumes demand follows a normal distribution) or average daily demand × buffer days (a simple rule of thumb).
This is a planning estimate, not a guarantee against stockouts — supplier delays, seasonality and promotions all sit outside the formula, so review the buffer against your actual service experience. All arithmetic runs in your browser; nothing is sent or stored.